Telling your DNO about a home battery: G98 or G99?

By Daan Haket · researched and written with an AI assistant · updated 15 November 2026

Short answer: Yes. Your network operator (DNO) has to know about a home battery, and your installer handles it. If everything in your home that can feed power out, battery included, adds up to no more than 16 A per phase (3.68 kW on a single-phase supply, 11.04 kW on three-phase), the installer notifies the DNO within 28 days of commissioning (G98). A battery together with solar panels is likely to go over that, and then G99 applies: an application to the DNO, made before anything is installed, with a fast-track route for some home batteries.

Your DNO (distribution network operator) runs the local cables. A battery can push power into them, so the DNO needs to know about it. Two rules decide how: Engineering Recommendation G98 for small systems and G99 for the rest. Here is what the Energy Networks Association’s guide says, and a quick check for your own set-up.

A battery counts as generation

The guide explicitly includes electricity storage devices in the 16 A rule.

“For the avoidance of doubt this includes electricity storage devices”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says network operators treat a battery as generation when they assess its effect on the network, so they need to know about it.

“DNOs treat electricity storage devices as generation, hence they need to be aware of electricity storage devices.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The 16 A line: add everything up

The ENA guide says the 16 A limit counts all generation in one home together: 3.68 kW on a single-phase supply and 11.04 kW on a three-phase supply.

“16 A per phase corresponds to 3.68 kW on a single-phase low voltage supply and 11.04 kW on a three-phase low voltage supply and refers to the aggregate Micro-generator capacity installed in a single premises”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says that for inverter-connected units, the G98 or G99 route depends on the total installed capacity of all the units together.

“Where you are installing multiple asynchronous or inverter connected generating units, the application process (as described in EREC G98 or EREC G99) is based on the total installed capacity of all the generating units.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

So you add the rated outputs of everything that can generate: the solar inverter and the battery’s inverter. If one hybrid inverter runs both panels and battery, it is one unit; ask your installer which capacity it will be registered at.

Quick check: G98 or G99?

ExampleSupplyTotal outputLimitRoute on these figures
No panels, 3 kW battery invertersingle-phase3 kW3.68 kWG98: installer notifies within 28 days
3.68 kW solar inverter + 5 kW batterysingle-phase8.68 kW3.68 kWG99: application to the DNO
Hybrid inverter rated 3.6 kW, panels and battery on itsingle-phase3.6 kW3.68 kWG98: installer notifies within 28 days
4 kW solar + 5 kW batterythree-phase9 kW11.04 kWG98: installer notifies within 28 days

Examples worked out on the 16 A rule only. On a three-phase supply the limit is 16 A on each phase, so ask your installer how the outputs are spread over the phases. Export limits and your DNO’s own process can change the answer.

Battery plus solar: usually G99

The ENA guide says a battery used together with solar panels is likely to take the total above 16 A per phase, so EREC G99 applies.

“electricity storage devices in conjunction with PV (or other technologies) to offset consumption, the total connected generation is likely to be above 16A / phase and hence EREC G99 applies”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says that under G99 you or your installer should apply to the DNO before any generating equipment, battery included, is installed.

“You or your installer should submit the application form to the DNO before any generation equipment is installed, as the DNO needs to assess the possible impact of your generating equipment on the distribution system.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says network operators run a fast-track application for some home-scale batteries, depending on the total connected generation.

“DNOs have implemented a fast-track application process, for some domestic scale electricity storage, depending on the total connected generation.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says the fast-track route cuts the time for the network operator to confirm whether the connection is acceptable from 45 days to 10 days or less.

“reduces the time for the DNO to provide confirmation that the connection is or is not acceptable from 45 days to 10 days or less”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says the fast-track route involves submitting the G99 Form A1-2 from the ENA Document Catalogue.

“This involves submitting the G99 Form A1-2, located in the ENA Document Catalogue”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

The ENA guide says the fast-track route does not apply if the battery is meant to run in island mode during a power cut; the standard G99 process applies then.

“If the electricity storage device is designed to operate in island mode (eg during a power outage) the fast-track process is not applicable and the standard EREC G99 process applies.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

New batteries since March 2026

The ENA guide says batteries installed from 1 March 2026 must switch from importing to exporting if the grid frequency falls below a set threshold.

“from 01 March 2026, new electricity storage devices are required to switch from import to export mode if the grid frequency falls below a defined threshold.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

This is a technical requirement for the battery and its inverter. Ask your installer to confirm in writing that the system you are buying meets it.

Under the line: the installer notifies

The ENA guide says the installer's notification to the DNO within 28 days of commissioning is a legal requirement.

“Your installer must notify the DNO within 28 days of commissioning the generating unit and provide them with information on the installation. This is a legal requirement.”
Source: UK Power Networks (ENA guide) (PDF), read 13 November 2026

What to ask your installer

The ENA guide quoted here is the March 2026 edition (version 3.0), in the copy published by UK Power Networks. Your own DNO’s current process is what counts, so ask for the route in writing. More on picking an installer: choosing a battery installer. Adding a battery to panels you already have: the retrofit guide.

Questions

Do I need to tell my DNO about a home battery?

Yes. Your network operator (DNO) has to know about a home battery, and your installer handles it. If everything in your home that can feed power out, battery included, adds up to no more than 16 A per phase (3.68 kW on a single-phase supply, 11.04 kW on three-phase), the installer notifies the DNO within 28 days of commissioning (G98). A battery together with solar panels is likely to go over that, and then G99 applies: an application to the DNO, made before anything is installed, with a fast-track route for some home batteries.

Is it G98 or G99 for a battery with solar panels?

The ENA guide says a battery used together with solar panels is likely to take the total above 16 A per phase, so G99 applies. Add up the rated outputs of the solar inverter and the battery: above 3.68 kW on a single-phase supply, or 11.04 kW on three-phase, means G99.

How long does a G99 application for a battery take?

With the fast-track route for some home batteries, the ENA guide says the time for the DNO to confirm whether the connection is acceptable drops from 45 days to 10 days or less. That is the DNO’s confirmation step, not the whole job: ask your installer for the full timeline and whether anything can be connected before the DNO accepts it.

Does backup power change the application?

Yes. The ENA guide says the fast-track route does not apply if the battery is meant to run in island mode during a power cut; the standard G99 process applies then.

Who sends the notification?

Your installer. The ENA guide says the installer must notify the DNO within 28 days of commissioning, and that this is a legal requirement.

Every quote on this page was checked again against its source on 12 November 2026.

Export limits (G100)

If your network operator will not accept everything a solar and battery system could export, an export limiter is a common way to get a connection agreed. It caps what leaves your home; the battery and your own use take the rest.

Export limiters must meet the ENA’s EREC G100 rules for export and import limiting schemes.

“Export and import limiting schemes need to be compliant with EREC G100”
Source: UK Power Networks (ENA guide) (PDF), read 15 November 2026